Filters
Question type

Study Flashcards

A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load per meter moved. An analyst has prepared the following distances and flow matrices:  Distances (meters)   Flows (loads per week  From/To  I  II  III  I 1020 II 10 III  From/To XYZX6090Y40160Z110140\begin{array}{l}\text { Distances (meters) } \quad\quad\quad\quad\quad\quad \text { Flows (loads per week }\\\begin{array}{rlll}\text { From/To } & \text { I } & \text { II } & \text { III } \\\hline \text { I } & - & 10 & 20 \\\text { II } & & - & 10 \\\text { III } & & & -\end{array}\quad\quad\begin{array}{rlll}\text { From/To } & \mathrm{X} & \mathrm{Y} & \mathrm{Z} \\\hline \mathrm{X} & - & 60 & 90 \\\mathrm{Y} & 40 & - & 160 \\\mathrm{Z} & 110 & 140 & -\end{array}\end{array} What is the distance (in meters) from area III to area I in this new facility?


A) 0
B) 10
C) 20
D) 30
E) 40

F) B) and D)
G) A) and E)

Correct Answer

verifed

verified

Which one of the following is not common to product layouts?


A) a high rate of output
B) specialization of labor
C) low unit costs
D) ability to adjust to changes in demand
E) special-purpose technology

F) A) and B)
G) All of the above

Correct Answer

verifed

verified

Intermittent processing can take the form of batch processing or a job shop.

A) True
B) False

Correct Answer

verifed

verified

A cafeteria line would be an example of a process-focused layout.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not an approach that companies use to achieve a smooth flow of production?


A) line balancing heuristics
B) parallel workstations
C) dynamic line balancing (cross-training workers)
D) mixed model line
E) Companies use all of these.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

The percentage of idle time in an assembly line is called cycle time.

A) True
B) False

Correct Answer

verifed

verified

False

Which of the following is not an information requirement for the design of a process layout?


A) a list of departments or work centers
B) a projection of work flows between the work centers
C) the distance between locations
D) the cost per unit of distance to move loads
E) a list of product cycle times for every product manufactured

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

E

A production line is to be designed for a job with three tasks. The task times are .3 minutes, 1.4 minutes, and .7 minutes. The minimum cycle time in minutes is:


A) .3.
B) .7.
C) 1.4.
D) 2.4.
E) .8.

F) A) and C)
G) C) and D)

Correct Answer

verifed

verified

C

In a product layout, the task of deciding how to assign work to specific stations is referred to as:


A) process balancing.
B) task allocation.
C) line balancing.
D) work allocation.
E) station balancing.

F) C) and D)
G) A) and C)

Correct Answer

verifed

verified

As compared to rigid automation, the benefits of flexible manufacturing systems include:


A) reduced labor requirements.
B) higher efficiency.
C) larger batch sizes.
D) significantly lower fixed costs.
E) significantly lower variable costs.

F) A) and E)
G) A) and D)

Correct Answer

verifed

verified

Continuous processing is the best way to produce customized output.

A) True
B) False

Correct Answer

verifed

verified

A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day. The tasks necessary to produce this product are:  Task  Time (secs)   Immediate Predecessor u30 none v30uw6ux12wy54xz30v,y\begin{array} { l l l } \text { Task } & \text { Time (secs) } & \text { Immediate Predecessor } \\\hline \mathrm { u } & 30 & \text { none } \\\mathrm { v } & 30 & \mathrm { u } \\\mathrm { w } & 6 & \mathrm { u } \\\mathrm { x } & 12 & \mathrm { w } \\\mathrm { y } & 54 & \mathrm { x } \\\mathrm { z } & 30 & \mathrm { v } , \mathrm { y }\end{array} If the company wants the output rate to be equal to demand, what is the last task performed at the second workstation in the balance which uses the minimum number of workstations?


A) u
B) v
C) w
D) x
E) y

F) A) and B)
G) A) and E)

Correct Answer

verifed

verified

Given the following line balance data:  Task  Predecessor  Time (seconds) t none 15ut14vt7wu6xv8yw,x10zy21\begin{array} { l c c } \text { Task } & \text { Predecessor } & \text { Time (seconds) } \\\hline \mathrm { t } & \text { none } & 15 \\\mathrm { u } & \mathrm { t } & 14 \\\mathrm { v } & \mathrm { t } & 7 \\\mathrm { w } & \mathrm { u } & 6 \\\mathrm { x } & \mathrm { v } & 8 \\\mathrm { y } & \mathrm { w } , \mathrm { x } & 10 \\\mathrm { z } & \mathrm { y } & 21\end{array} What is the minimum possible cycle time?

Correct Answer

verifed

verified

An advantage of a U-shaped production line is that:


A) it is less compact.
B) communication is reduced among employees.
C) workers are specialists.
D) work assignments are more rigid.
E) it is more efficient than a traditional product layout.

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Key aspects of the process selection challenge include _________ and __________.


A) information technology; marketing strategy
B) process flexibility; marketing strategy
C) capital intensity; process flexibility
D) marketing strategy; operations strategy
E) capacity planning; marketing strategy

F) A) and B)
G) B) and C)

Correct Answer

verifed

verified

The minimum number of workstations for a production line is determined in part by the desired output rate.

A) True
B) False

Correct Answer

verifed

verified

The grouping of equipment by the operations needed to perform similar work for part families is:


A) product layout.
B) cellular manufacturing layout.
C) functional layout.
D) fixed-position layout.
E) process layout.

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

"Balance delay" is another name for the percentage of idle time in a process layout.

A) True
B) False

Correct Answer

verifed

verified

A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load per meter moved. An analyst has prepared the following distances and flow matrices:  Distances (meters)   Flows (loads per week  From/To  I  II  III  I 1020 II 10 III  From/To XYZX6090Y40160Z110140\begin{array}{l}\text { Distances (meters) } \quad\quad\quad\quad\quad\quad \text { Flows (loads per week }\\\begin{array}{rlll}\text { From/To } & \text { I } & \text { II } & \text { III } \\\hline \text { I } & - & 10 & 20 \\\text { II } & & - & 10 \\\text { III } & & & -\end{array}\quad\quad\begin{array}{rlll}\text { From/To } & \mathrm{X} & \mathrm{Y} & \mathrm{Z} \\\hline \mathrm{X} & - & 60 & 90 \\\mathrm{Y} & 40 & - & 160 \\\mathrm{Z} & 110 & 140 & -\end{array}\end{array} How many least costly process layouts are there?


A) 1
B) 2
C) 3
D) 4
E) 5

F) B) and E)
G) A) and C)

Correct Answer

verifed

verified

A company needs to locate three departments (X, Y, and Z) in the three areas (I, II, and III) of a new facility. They want to minimize interdepartmental transportation costs, which are expected to be $.50 per load meter moved. An analyst has prepared the following flow and distance matrices:  Distances (meters)   Flows (loads per week  From/To  I  II  III  I 1020 II 10 III  From/To XYZX080Y30150Z100130\begin{array}{l}\text { Distances (meters) } \quad\quad\quad\quad\quad\quad \text { Flows (loads per week }\\\begin{array}{rlll}\text { From/To } & \text { I } & \text { II } & \text { III } \\\hline \text { I } & - & 10 & 20 \\\text { II } & & - & 10 \\\text { III } & & & -\end{array}\quad\quad\begin{array}{rlll}\text { From/To } & \mathrm{X} & \mathrm{Y} & \mathrm{Z} \\\hline \mathrm{X} & - & 0 & 80 \\\mathrm{Y} & 30 & - & 150 \\\mathrm{Z} & 100 & 130 & -\end{array}\end{array} What is the distance (in meters) from area III to area I of this new facility?


A) 0
B) 10
C) 20
D) 30
E) 40

F) All of the above
G) A) and C)

Correct Answer

verifed

verified

Showing 1 - 20 of 150

Related Exams

Show Answer