Filters
Question type

Study Flashcards

A Dallas firm manufactures dishwashing liquid.The manager wants to evaluate the performance of station 3,the bottleneck in the filling operation.The following output report is given. A Dallas firm manufactures dishwashing liquid.The manager wants to evaluate the performance of station 3,the bottleneck in the filling operation.The following output report is given.   Calculate the cumulative deviation of the output at the end of period 3. A) -20 B) -40 C) 10 D) 20 E) 40 Calculate the cumulative deviation of the output at the end of period 3.


A) -20
B) -40
C) 10
D) 20
E) 40

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

The following jobs are waiting to be scheduled.Today is day 9.Determine the sequence of jobs by using LCFS as a priority rule. The following jobs are waiting to be scheduled.Today is day 9.Determine the sequence of jobs by using LCFS as a priority rule.   A) D-C-A-E-B B) A-B-C-D-E C) B-E-A-C-D D) B-E-C-A-D E) B-E-C-D-A


A) D-C-A-E-B
B) A-B-C-D-E
C) B-E-A-C-D
D) B-E-C-A-D
E) B-E-C-D-A

F) All of the above
G) None of the above

Correct Answer

verifed

verified

Using the following data,calculate the average job tardiness. Using the following data,calculate the average job tardiness.     A) 6 days B) 1.5 days C) -2 days D) -8 days E) 3 days


A) 6 days
B) 1.5 days
C) -2 days
D) -8 days
E) 3 days

F) C) and D)
G) D) and E)

Correct Answer

verifed

verified

B

Operation sequencing creates a work center plan based on available _______ and ______.


A) capacity,priorities
B) demand,priorities
C) capacity,demand
D) capacity,rules
E) staff,management

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Load and progress charts are examples of _____________________.

Correct Answer

verifed

verified

Optimized production technology (OPT) was introduced by Eli ____________________.


A) Goldratt
B) Manning
C) Jefferson
D) Rosenblatt
E) Strasburg

F) B) and D)
G) None of the above

Correct Answer

verifed

verified

A

Usage and activation of a resource are not the same.

A) True
B) False

Correct Answer

verifed

verified

What does "negative lateness" mean?


A) The job is finished after its due date.
B) The job is finished on its due date.
C) The job is finished before its due date.
D) The job is not finished.
E) The job has not started.

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

Using the following data,calculate the average job lateness and average job tardiness. Using the following data,calculate the average job lateness and average job tardiness.

Correct Answer

verifed

verified

lateness =...

View Answer

What is throughput?


A) the quantity of finished goods that can be sold
B) the quantity of items moved at the same time from one resource to the next
C) the quantity of work-in-process inventory
D) the quantity produced at a resource before the resource is switched over to produce another product
E) the average flow time of the system

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

Define what slack is.

Correct Answer

verifed

verified

Slack is the amount ...

View Answer

The two different approaches to load work centers in job-shop scheduling are __________________.


A) load chart and process chart
B) finite loading and infinite loading
C) input control and output control
D) fixed routings and line balancing
E) makespan and linear programming

F) All of the above
G) B) and C)

Correct Answer

verifed

verified

Using the S/RO rule,which of the following jobs will be scheduled first?


A) the first job that arrives at a work center
B) the job with the least slack per remaining operations
C) the job with the highest slack per remaining operations
D) the job with the smallest ratio of time remaining until due date to process time remaining
E) the job with the largest ratio of time remaining until due date to process time remaining

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

If the schedule shows a 5 day slack between the end of Task A and start of Task B,this means:


A) you must start Task B as soon as Task A ends.
B) Task B start is late.
C) Task A is taking longer to complete.
D) Task A and Task B should be performed concurrently.
E) Task B start can be delayed up to 5 days after Task A's scheduled completion.

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

What is a transfer batch?


A) the quantity of finished goods that can be sold
B) the quantity of items moved at the same time from one resource to the next
C) the quantity of work-in-process inventory
D) the quantity produced at a resource before the resource is switched over to produce another product
E) the quantity of items needed to attain a full truckload (TL) shipping rate

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

When were Gantt charts developed?


A) early 1800s
B) early 1900s
C) early 1920s
D) early 1940s
E) early 1960s

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Slim-Quick Inc.produces a variety of nutritional diet products.Management wants to evaluate the performance of Work Center 10,the bottleneck in the packaging line.They are particularly worried about the backlogging problem in the work center.The following input/output report is given. Slim-Quick Inc.produces a variety of nutritional diet products.Management wants to evaluate the performance of Work Center 10,the bottleneck in the packaging line.They are particularly worried about the backlogging problem in the work center.The following input/output report is given.     The initial backlog was 100 hours.Based on the above information,calculate the backlog hours of Work Center 10 at the end of period 3. A) 100 B) 110 C) 140 D) 150 E) 200 Slim-Quick Inc.produces a variety of nutritional diet products.Management wants to evaluate the performance of Work Center 10,the bottleneck in the packaging line.They are particularly worried about the backlogging problem in the work center.The following input/output report is given.     The initial backlog was 100 hours.Based on the above information,calculate the backlog hours of Work Center 10 at the end of period 3. A) 100 B) 110 C) 140 D) 150 E) 200 The initial backlog was 100 hours.Based on the above information,calculate the backlog hours of Work Center 10 at the end of period 3.


A) 100
B) 110
C) 140
D) 150
E) 200

F) B) and C)
G) B) and E)

Correct Answer

verifed

verified

Which of the following scheduling rules is a global priority rule?


A) first come,first served
B) last come,first served
C) earliest due date
D) shortest processing time
E) slack per remaining operations

F) C) and E)
G) A) and B)

Correct Answer

verifed

verified

E

The following jobs are waiting to be scheduled.Today is day 9.Determine the sequence of jobs by using SPT as a priority rule. The following jobs are waiting to be scheduled.Today is day 9.Determine the sequence of jobs by using SPT as a priority rule.    A) D-A-C-E-B B) B-E-C-A-D C) C-D-E-A-B D) B-A-E-D-C E) A-D-C-E-B


A) D-A-C-E-B
B) B-E-C-A-D
C) C-D-E-A-B
D) B-A-E-D-C
E) A-D-C-E-B

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

Terry's cycle shop standard hour input/output report is below.Calculate the output deviation and backlog hours for periods 1,2,3,and 4. Terry's cycle shop standard hour input/output report is below.Calculate the output deviation and backlog hours for periods 1,2,3,and 4.

Correct Answer

verifed

verified

Output deviation = -...

View Answer

Showing 1 - 20 of 131

Related Exams

Show Answer